SciRepID - Cost Analysis Due to the Addition of Working Time on Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3 Blitar City


Cost Analysis Due to the Addition of Working Time on Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3 Blitar City

International Journal of Industrial Innovation and Mechanical Engineering
Asosiasi Riset Ilmu Teknik Indonesia (ARITEKIN)

📄 Abstract

Prolonged road damage disrupts community mobility, logistics activities, and reduces road user safety. The road maintenance project on Jl. Ir. Soekarno in Blitar City, which was planned to be completed in 120 days with a budget of Rp1.16 billion, experienced a delay of 8 days due to time management constraints. This study aims to evaluate the use of the Time Cost Trade Off (TCTO) method to accelerate project completion without reducing the quality of work. The TCTO method is used to analyze the relationship between time and cost. This research proposes additional overtime working hours of 2 hours per day with the assumption of resources according to the Cost Budget Plan (RAB). The results show that with this method, the project can be completed in 117 days at a total cost of Rp1,342,177,724. Although it requires additional costs, this acceleration allows the project to be completed faster than the previous condition

🔖 Keywords

#Additional costs; Project delay; Road damage; Road maintenance; Time Cost Trade Off (TCTO)

ℹ️ Informasi Publikasi

Tanggal Publikasi
31 August 2025
Volume / Nomor / Tahun
Volume 2, Nomor 3, Tahun 2025

📝 HOW TO CITE

Eka Shodiq Permadi; Hanie Teki Tjendani; Budi Witjaksana, "Cost Analysis Due to the Addition of Working Time on Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3 Blitar City," International Journal of Industrial Innovation and Mechanical Engineering, vol. 2, no. 3, Aug. 2025.

ACM
ACS
APA
ABNT
Chicago
Harvard
IEEE
MLA
Turabian
Vancouver

🔗 Artikel Terkait dari Jurnal yang Sama

📊 Statistik Sitasi Jurnal

Tren Sitasi per Tahun