SciRepID - Optimizing Time Calculation with Extended Working Hours in the Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3, Blitar City


Optimizing Time Calculation with Extended Working Hours in the Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3, Blitar City

International Journal of Mechanical, Industrial and Control Systems Engineering
Asosiasi Riset Ilmu Teknik Indonesia (ARITEKIN)

📄 Abstract

Road maintenance is a strategic effort to support community mobility and economic development. This study aims to determine the optimal duration and analyze the cost impacts of implementing the Time Cost Trade Off (TCTO) method. The method is applied through critical path analysis and adding overtime hours to reduce the project duration. Data is collected from project documents such as daily reports, S-curves, and cost budget plans, then analyzed using Microsoft Project software. The results show that the project duration can be shortened to 117 days with an additional cost of IDR 176,614,724.00, which is lower than the potential delay penalty of 1% per day. This adjustment leads to a time savings of 8.6% without causing significant changes to the project's organizational structure. The TCTO method proves to be a practical solution for addressing delays while maintaining a balance between time and cost.

🔖 Keywords

#Time Cost Trade Off (TCTO); Road maintenance; Optimal duration; Additional cost; Time saving

ℹ️ Informasi Publikasi

Tanggal Publikasi
24 January 2025
Volume / Nomor / Tahun
Volume 2, Nomor 1, Tahun 2025

📝 HOW TO CITE

Eka Shodiq Permadi; Hanie Teki Tjendani; Budi Witjaksana, "Optimizing Time Calculation with Extended Working Hours in the Periodic Road Maintenance Project on Jl. Ir. Soekarno Ruas 3, Blitar City," International Journal of Mechanical, Industrial and Control Systems Engineering, vol. 2, no. 1, Jan. 2025.

ACM
ACS
APA
ABNT
Chicago
Harvard
IEEE
MLA
Turabian
Vancouver

🔗 Artikel Terkait dari Jurnal yang Sama

📊 Statistik Sitasi Jurnal

Tren Sitasi per Tahun