Publication Search

80,083 articles from 753 journals · 2,111 citations tracked

Showing 1-5 of 5

Analytics

Roseli Coo, Priccilia; Khamelda, Lila; Sonny Yoedono, Benedictus

Jurnal Teknik Sipil 2026 Jurnal Teknik Sipil

The road project serving as access to Lambo Dam in Rendubutowe Village, South Aesesa District, Nagekeo Regency, East Nusa Tenggara, uses various types of heavy equipment. The analysis method was carried out by recalculating productivity based on field data and references. Productivity calculations were related to the work volume in order to obtain daily productivity and the required duration. Therefore, theoretical calculation knowledge derived from previous studies was needed. Heavy equipment productivity was then analyzed to determine time efficiency. The subgrade work and pavement layer work on the road project to Lambo Dam, located in Rendubutowe Village, South Aesesa District, Nagekeo Regency, East Nusa Tenggara, had a road length of 6.3 km and a road width of 6 m. However, the observation was limited to a 1 km section from Station (Sta) 0+500 to Sta 1+500. The results obtained were productivity and duration for excavation work using an excavator and dump truck, each at 1785.6 m³/day in 4.52 days. Embankment work using an excavator and dump truck each had a productivity of 892.8 m³/day for 3.82 days, a bulldozer of 43,200 m³/day in 0.07 days, and a Vibro Roller of 168 m³/day in 20.27 days. Base course work used an excavator and dump truck with a productivity of 892.8 m³/day in 2.02 days, a motor grader of 23,372.8 m2/day, and a Vibro Roller of 168 m³/day for 10.71 days. Surface course work used a concrete Mixer truck with a productivity of 43.4 m³/day for 36.72 days. Heavy equipment productivity is influenced by the number of units used; the insufficient use of excavators causes dump truck productivity to be less than optimal in transporting excavation and embankment materials. Likewise, Vibro Rollers are needed in more than one unit so that the project can be completed faster

Widya Lestari; Hepriyandi Luwyk Djanas Usup; Yustinus Hendra Wiryanto; Novalisae Novalisae; I Putu Putrawianta

Jurnal Riset Rumpun Ilmu Teknik 2026 Pusat riset dan Inovasi Nasional

Coal hauling activities are an important part of mining operation because they affect production continuity, cycle time efficiency, and operational safety. This study aims to analyze the requirements of road support equipment on the coal hauling road from Sector 4 to the new Coal Processing Plant (CPP) at PT. Asmin Bara Bronang, Central Kalimantan. Based on road geometry, traffic density, California Bearing Ratio (CBR), and Unsurfaced Road Condition Index (URCI). The research method used was applied research with a quantitative approach. Primary data ware collected through field measurements consisting of road geometri observations, traffic density observations, Dynamic Cone Penetrometer (DCP) testing to obtain CBR values, and road surface condition assessment using the URCI method. Secondary data were obtained from the company records. The results showed that the hauling road has a total length of 9.1 km with an average width of 16 m, and grade values ranging from -7.68% to 10.52%, which are still below the maximum standard of 12%. Traffic density reached 184 dump trucks/day, for coal hauling and 62 units/day for construction material transportation, indicating high traffic intensity. CBR values ranged from 7% to 100%, showing variations in subgrade bearing capacity. The URCI value ranged from 72,50 to 91.00, indicating fair to good road conditions. Based on the analysis of road conditions and maintenance area requirements, the recommended support equipment for maintaining the hauling road consists of 1 motor grader unit, 1 compactor unit, 1 bulldozer unit, and 1 water truck unit.

Wisnu Mangarso, Aryaditya; Khamelda, Lila; Sunik

Jurnal Teknik Sipil 2025 Jurnal Teknik Sipil

The subgrade work and road pavement layer work carried out in the Sewan Munukania road project, Petam Village, South Sarmi District, Papua, were performed 14.900 km with a road width of 8 m. The analysis was conducted on the performance of heavy equipment used in the subgrade and pavement layer works in the Sewan Munukania road project. The results showed that the heavy equipment productivity for excavation work of 225 m³ used 1 excavator with a productivity of 1,519.672 m³/day and a duration of 0.14 days, while 3 dump trucks achieved 345.03 m³/day with a duration of 0.65 days. Coral fill work of 644.25 m³ used 1 excavator with a productivity of 736.75 m³/day and a duration of 0.87 days, 3 dump trucks with 7.89 m³/day in 3.88 days, 1 motor grader with 1,628.57 m³/day in 0.05 days, and 1 vibro roller with 73.45 m³/day in 1.21 days. Sand fill work of 4.56 m³ used 1 excavator with a productivity of 1,150 m³/day and a duration of 0.003 days, 3 dump trucks with 43.15 m³/day in 0.005 days, 1 motor grader with 1,680 m³/day in 0.0003 days, and 1 vibro roller with 112.84 m³/day in 0.005 days. The subbase layer work of 11,920 m³ used 1 excavator with a productivity of 105.25 m³/day in 16.17 days, 3 dump trucks with 7.89 m³/day in 71.94 days, 1 motor grader with 244.28 m³/day in 6.97 days, and 1 vibro roller with 528.15 m³/day in 22.56 days. The base layer work of 35,760 m³ used 1 truck mixer with a productivity of 44.59 m³/day in 801.97 days. The surface layer of 2,384 m³ used an asphalt finisher with a productivity of 267.19 m³/day in 8.9 days, and a tandem roller with 34.23 m³/day in 6.54 days.

Kenjam, Agustinus; Khamelda, Lila; Sunik

Jurnal Teknik Sipil 2025 Jurnal Teknik Sipil

Subgrade work and road pavement layer work carried out on the Oeprigi–Haekto road project were implemented along 1,000 m with a road width of 6 m. The performance of heavy equipment used for foundation and pavement works on the Oeprigi–Haekto road project was analyzed. The results show that for excavation work of 1,229.3 m³, one Excavator has a productivity of 1,237.04 m³/day with a duration of 0.99 days, while nine dump trucks have a productivity of 4,888.08 m³/day with a duration of 0.26 days. Embankment work of 182.02 m³ uses one Excavator with a productivity of 1,237.04 m³/day and a duration of 0.16 days, nine dump trucks with 4,888.08 m³/day in 0.53 days, one motor grader with 5,953.52 m³/day in 0.43 days, and two vibro rollers with 283.52 m³/day in 9.07 days. The subbase layer work of 1,200 m³/day uses one Excavator with a productivity of 1,237.04 m³/day in 0.18 days, nine dump trucks with 2,333.05 m³/day in 0.53 days, one motor grader with 5,953.52 m³/day in 0.21 days, and two vibro rollers with 283.52 m³/day in 4.24 days. The base layer work of 800 m³/day uses one Excavator with a productivity of 1,237.04 m³/day in 0.65 days, nine dump trucks with 2,333.05 m³/day in 0.54 days, one motor grader with 5,953.52 m³/day in 0.14 days, and two vibro rollers with 283.52 m³/day. The surface layer of 160 m³ uses an asphalt finisher with a productivity of 47.81 m³/day in 0.42 days and a tandem roller with 24.11 m³/day in 0.83 days.  

Ivanka Thamara Victorya Bannegau, Rivelya; Bahtiar Bahtiar; Helen G. Wayangkau

Jurnal Sipil Terapan 2024 Fakultas Teknik Universitas Cenderawasih

Roads in Manokwari City still need a lot to be improved, especially on the Pegaf city boundary road - South Manokwari district, because this road connects the border between the City and the district.... This study aims to calculate the productivity of heavy equipment working on road improvement work, Analyzing the balance of road improvement work tools and knowing the total cost and time required in road improvement projects. So that this research is expected to be useful for optimizing the performance of road sections and being able to provide solutions to problems that occur and can provide an overview of the process of using heavy equipment that is effective and efficient. Productivity is the ability to produce something, so it can be said that heavy equipment productivity is the ability of heavy equipment to produce something per unit of time. In general, heavy equipment work production has the same calculation principles. The basic principles of calculating heavy equipment work production are 4 steps, namely calculating actual capacity, cycle time, calculating gross work production (PKK) and calculating actual work production (PKA). So it can be concluded that the productivity of ordinary embankment excavator 173.68m3 / hour, dump truck 10 tons of ordinary embankment 45.58m3 / hour, optional embankment 36.3m3 / hour, asphalt foundation layer (HRS Base) 7.91m3 / hour, Dump truck 4 tons of Class A aggregate layer 4.02m3 / hour, Class B aggregate layer 4.06m3/hour, motor grader 315m2/hour regular embankment, 174.30 m3/hour optional embankment, 561m2/hour pavement preparation, Class A aggregate layer 274.63m3/hour, Class B aggregate layer 274.63m3/hour, vibratory roller regular embankment 159.36 m3/hour, class A aggregate layer 77.02m3/hour, class B aggregate layer 77.02m3/hour asphalt distributor binder layer 4980 liters, air compressor binder work 1365.35 liters, asphalt finisher asphalt foundation layer (HRS Base) 69.85 tons, tandem roller regular embankment 39.84m3/hour, preparation of the road body 272.98m3 / hour, paving 86.59m3 / hour, wheel loader preferred embankment 117.58m3 / hour, class A aggregate layer 114.98m3 / hour, class B aggregate layer 116.53m3 / hour and tire roller paving 104.06 tons and the total cost of all equipment rental is Rp. 254,091,569.