SciRepID - Analisa Pengendalian Waktu Dan Biaya Proyek ITC Pole Fibre Optic Menggunakan Metode Earned Value: Studi Kasus: PT.LUM

📅 30 November 2023
DOI: 10.62951/switch.v1i6.91

Analisa Pengendalian Waktu Dan Biaya Proyek ITC Pole Fibre Optic Menggunakan Metode Earned Value: Studi Kasus: PT.LUM

Switch : Jurnal Sains dan Teknologi Informasi
Asosiasi Riset Teknik Elektro dan Informatika Indonesia (ARTEII)

📄 Abstract

This research aims to analyze time and cost control on the ITC Pole Fiber Optic project managed by PT. LUM uses the Earned Value Management (EVM) method. EVM is an effective method for measuring project performance and progress by combining cost, time and completed work data. This case study uses secondary data obtained from project progress reports and PT financial data. LUM. Analysis is carried out to identify cost variance (CV) and schedule variance (SV) as well as cost performance index (CPI) and schedule performance index (Schedule Performance Index - SPI). The research results show that the ITC Pole Fiber Optic project experienced several deviations from the planned budget and schedule, with CV and SV showing negative values ​​at several project stages, indicating cost overruns and delays. The CPI and SPI values ​​obtained also provide an overview of the efficiency and effectiveness of project implementation. Based on these findings, several improvement steps are recommended to optimize time and cost control to improve project performance in the future. This research makes an important contribution in providing insight into the application of EVM in fiber optic installation projects and can be used as a reference in managing similar projects in the future.

🔖 Keywords

#Earned Value Management; Project Control; Cost Variances; Schedule Variances; Project Performance; Fiber Optic Installation

ℹ️ Informasi Publikasi

Tanggal Publikasi
30 November 2023
Volume / Nomor / Tahun
Volume 1, Nomor 6, Tahun 2023

📝 HOW TO CITE

Indra Bakti; Mohamad Firdaus, "Analisa Pengendalian Waktu Dan Biaya Proyek ITC Pole Fibre Optic Menggunakan Metode Earned Value: Studi Kasus: PT.LUM," Switch : Jurnal Sains dan Teknologi Informasi, vol. 1, no. 6, Nov. 2023.

ACM
ACS
APA
ABNT
Chicago
Harvard
IEEE
MLA
Turabian
Vancouver

🔗 Artikel Terkait dari Jurnal yang Sama

📊 Statistik Sitasi Jurnal

Tren Sitasi per Tahun